Cement floor installed in Southgate Honey Shed | JCB & SONS. We install the new cement floor on Tuesday for the Honey Shed Build. Thanks to the Eccles Family for pitching in on their project and helping get the cement into the building and having an amazing meal for us.
We installed a power trowel finish on this floor to make it nice and smooth for easy clean up and easy to roll equipment around on the floor.
The overhead doors, doors, windows, Roxul insulation and the remainder of the lumber is on site and ready to go to complete this project.
New 2x6 walls which will be insulated are installed partitioning the extraction room from the shop/storage area. We also framed in a utility room and small 3pc bathroom. This will allow the water to stay on in the building without having to heat the whole building. There will be a floor framed above the utility/bathroom walls allowing storage space.
The extraction room has a centre gutter drain to make equipment washing really easy. We also didn't power trowel the extraction room floor as smooth as the shop area as it will be getting an epoxy coating to keep the room easy to sanitize and also help protect the cement.